1.5.2.4 Subproject Manager's Review
 Chair
Subproject manager
 Objectives
- To understand progress of work against the overall plan
- To review and optimize short term plans
- To discuss exception areas and raise issues or changes accordingly
- To discuss requirements for other reviews.
 Participants
- Subproject manager
- Team leaders
- Project office manager
- Other staff invited by you.
 Frequency
Weekly
 Duration
Two hours maximum
 Prerequisites
Management system up-to-date
 Agenda
- Review of actions from previous meeting
- Status of subproject against plan and outlook for next period
- Review of outstanding issues (not already covered)
- Review of outstanding and newly approved changes
- Other items as required.
 Outputs
- Immediate handwritten minutes - use actions from meetings form
- Brief summary report to you covering overall progress, milestones, and issues.[subject_BPR]