英文标题:
《Quantitative Cost and Schedule Risk Analysis of Nuclear Waste Storage》
---
作者:
Alexander Budzier, Bent Flyvbjerg, Andi Garavaglia, and Andreas Leed
---
最新提交年份:
2019
---
英文摘要:
This study provides an independent, outside-in estimate of the cost and schedule risks of nuclear waste storage projects. Based on a reference class of 216 past, comparable projects, risk of cost overrun was found to be 202% or less, with 80% certainty, i.e., 20% risk of an overrun above 202%. Based on a reference class of 200 past, comparable projects, risk of schedule overrun was found to be 104% or less, with 80% certainty, i.e., 20% risk of overrun above 104%. Cost risk and schedule risk are both substantial for nuclear waste storage projects.
---
中文摘要:
本研究为核废物贮存项目的成本和进度风险提供了一个独立的、由外而内的估计。根据216个过去可比项目的参考类别,发现成本超支风险为202%或以下,80%的确定性,即超过202%的超支风险为20%。根据200个过去可比项目的参考类别,发现进度超限风险为104%或以下,80%的确定性,即超过104%的风险为20%。对于核废物贮存项目而言,成本风险和进度风险都是巨大的。
---
分类信息:
一级分类:Quantitative Finance 数量金融学
二级分类:General Finance 一般财务
分类描述:Development of general quantitative methodologies with applications in finance
通用定量方法的发展及其在金融中的应用
--
---