Sample:

367. Poka-yoke uses a number of devices to mistake proof a process.
Which of the following would NOT be included?



A
Fixture templates


B
Electric relays


C
Buzzer or light signals


D
Self-check inspections



The key question word is devices.
Inspections, for the most part, have human components and can be suspect.
However, most experts in the area of poka-yoke do recommend source, self and successive check methods.



Answer D is the correct, incorrect, choice.


Reference:
CSSBB Primer, Section X - 42 (and logic).



368. Consider the following definition: ""The best combination of machines and people working together to produce a product or service at a particular point in time.""
What lean concept is being described?



A
Standard work


B
A future state map


C
The value stream


D
Ultimate cycle time



The quote comes from Sharma (2001) and describes standard work.
The other answers were fabricated to sound good.



Answer A is correct.


References:
CSSBB Primer, Section X - 44 and Sharma, A., & Moody, P. (2001). The Perfect Engine: How to Win in the New Demand Economy by Building to Order with Fewer Resources.
New York: The Free Press.



369. Standard work sheets are required for standard operations.
What elements are included on the sheets?



I.
Cycle time based on takt time


II.
Work sequence - the order of operations


III.
Standard inventory on hand


IV.
The annual or semi-annual review date



A
I, II and III only


B
I, II and IV only


C
I, III and IV only


D
II, III and IV only



The answer choices would certainly indicate that one of the items is incorrect.
Shingo wrote that the operating sheets should be improved continuously.
Sharma allowed for monthly reviews.
Obviously, item IV is incorrect.



Answer A is correct.


Reference:
CSSBB Primer, Section X - 44.



370. Identify the lean enterprise technique in which the videotaping of a segment of the operation is helpful:



A
SMED


B
TPM


C
Takt


D
FIFO



The distractor choices of inventory rotation (FIFO - first in, first out) and Takt time are fairly weak options.
Total productive maintenance (TPM) could have some video tape applications.
However, the best option is single minute exchange of dies (SMED).
The timing of rapid die change out can really benefit from video taping the process.
The tape can be run in slow motion to observe hinderances and delay areas, etc.



Answer A is correct.


Reference:
CSSBB Primer, Section X - 47 (and logic).



371. In the SMED system what is the real meaning of the single minute concept?



A
That dies will be exchanged in 1 minute or less


B
That dies will be exchanged in less than 5 minutes


C
That dies will be exchanged in less than 10 minutes


D
That dies will be exchanged in less than 15 minutes



Authorities differ slightly on the definition.
They all agree that it doesn't mean one minute or less (although desirable).
Some say it refers to a single digit of time (in minutes).
In this case, 9 minutes qualifies.
Others say under 10 minutes.



Answer C is considered correct.


Reference:
CSSBB Primer, Section X - 45 and X - 56.


二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

全部回复
2011-8-23 14:48:28
Please help me to get this file
Babu
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

2011-8-23 14:49:11
Please help me to get this file, reply me at babs4chat@gmail.com
Babu

二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

2011-11-25 17:33:21
Can you share this with me
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

2012-1-3 22:02:04
好东西。。
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

2012-3-14 10:38:42
能否发给我一份呢谢谢
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

点击查看更多内容…
相关推荐
栏目导航
热门文章
推荐文章

说点什么

分享

扫码加好友,拉您进群
各岗位、行业、专业交流群