METHOD STATEMENT
FOR BRIDGE,
MICRO
PILING
, LOAD TEST
AND CONCRETE WORKS
CONSTRUCTION METHOD FOR THE BRIDGE
OBJECTIVE
The objective of this method statement is to describe and outline a working methodology to ensure a fair degree of control, attention and consideration had
been
given to the construction of Bridge over Sg.
Dapu
, Sarawak.
SCOPE OF WORK
The scope of work will cover the work methodology for:
o Site Preparation
o Pilling Work (Bored Pile)
o Testing of Piles (PDA, Load Test and Pile ...