全部版块 我的主页
论坛 经济学论坛 三区 微观经济学
1246 2
2009-11-30
SportStuff makes 2 kinds of sports bag, a Classic and a Luxury bag.
Profit on the Classic bag is £40 and on the Luxury bag £50. The company are planning their weekly work schedule, they want to maximise their profit. The production mix is subject to certain constraints. They must make at least 40 bags in total per week and they can make no more than 60 of the Luxury bag.
The level of production is restricted by the weekly labour availability according to the following table:


Classic

Requirement

Luxury Requirement

Availability

Fabric Construction

20

30

2400

Frame Construction

30

20

3000

i)
Formulate the objective function and the constraints.


ii)
Draw an accurate graph showing the constraints, the feasible region, and the
vertices of the feasible region.

iii)
Find the optimal solution for the problem using the graphical method and by
calculating profit at each vertex.

iv)
Identify slack/tight variables.

v)
Calculate the shadow price for both fabric and frame construction.

vi)
If the company could increase the time available for fabric construction, by
how much should it be increased? What would be the best product mix and the
resulting profit?

vii)
Looking at the original problem, what would be the optimal solution if the profit on the Luxury bag was increased to £60, the profit on the Classic bag was to remain at £40.

viii)
Following on from vii), if the constraint on the number of Luxury bags was increased to a maximum of 80 per week, what is the best solution?

Comment on your answer.
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

全部回复
2009-11-30 16:30:05
英文的,看着费劲
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

2009-11-30 18:46:56
这个题又画图又有那么多变量,在本子上做好做,传到论坛上真是够费劲的,期待好心又勤快的坛友
二维码

扫码加我 拉你入群

请注明:姓名-公司-职位

以便审核进群资格,未注明则拒绝

相关推荐
栏目导航
热门文章
推荐文章

说点什么

分享

扫码加好友,拉您进群
各岗位、行业、专业交流群